Sample change order

Fictional customer and contractor. The document is ScopeAccord’s Wisconsin change order template, filled in for a customer who asked for the dining room to be painted too. Signature lines stay blank until the document is sent for signature.

Create my first change orderFree for 7 days. No credit card required.← Back to ScopeAccord

Sample Remodeling

100 Example Street, Exampleville, WI 53000
Change Order

To Home Remodeling Contract — State of Wisconsin

Non-signature fields complete
  • Change Order No. 1 · Date October 19, 2026
  • Signatures, printed names, and signature dates remain blank for signing

1Reference to Original Contract

This Change Order modifies the Home Remodeling Contract dated October 5, 2026 (the “Contract”) between the Contractor (“Seller”) and Owner(s) (“Buyer”) identified below for work at the Property located at:

Property address: 200 Sample Avenue, Exampleville, WI 53000

(name and business address): Sample Remodeling LLC, 100 Example Street, Exampleville, WI 53000

: Jordan Example

This Change Order is made in writing and signed by both parties as required for changes to written home improvement contracts under Wis. Admin. Code § ATCP 110.05(1).

2Description of Change

The Scope of Work is changed as follows, including work added, deleted, or modified and the specific products, materials, brands, models, grades, and quantities involved:

Add painting of the dining room, which was not in the original scope: patch nail holes, prime patched areas, and apply two coats of interior latex paint to the walls and one coat of flat ceiling paint to the ceiling. Owner selects the colors before work starts. Contractor supplies paint and materials.

Attachments incorporated into this Change Order: None

Substitution of products or materials. If this Change Order substitutes any product or material for one specified in the Contract or represented by Contractor, Owner’s signature below constitutes Owner’s prior written consent to that substitution as required by Wis. Admin. Code § ATCP 110.023(1). The substituted item(s) and the item(s) they replace are identified in the description above.

3Adjustment to Contract Price

Original Contract Price: $18,500

Net change by prior Change Orders: $0

This Change Order: ADDS $850

New Contract Price including this Change Order: $19,350

Payment for this Change Order is due: Due with the final payment under the Contract

Unless stated otherwise above, the price stated in this Change Order is a fixed price that includes all labor, materials, equipment, permits, supervision, overhead, and profit associated with the changed work. Payments remain subject to the trust fund provisions of Wis. Stat. § 779.02(5).

4Adjustment to Schedule

The start and completion dates in the Contract are: UNCHANGED.

As provided by Wis. Admin. Code §§ ATCP 110.027 and 110.05, no change in the performance deadlines of a written home improvement contract is effective unless the Owner agrees to the change in writing. Owner’s signature below constitutes that written agreement to the revised deadlines, if any, stated in this Section.

5Permits for Changed Work

Additional building or construction permits required: None

If additional permits are required, Contractor shall obtain them before starting the changed work, as required by Wis. Admin. Code § ATCP 110.03, and shall furnish Owner copies of any required inspection certificates before final payment for the changed work.

6Effect on Contract

Except as expressly modified by this Change Order, all terms and conditions of the Contract remain unchanged and in full force, including the construction lien notice, warranty, insurance, lien waiver, and dispute resolution provisions, all of which apply to the changed work. This Change Order is not effective, and Contractor shall not perform or charge for the changed work, until it has been signed by both Owner and Contractor. Contractor shall provide Owner a completed, signed copy of this Change Order before beginning the changed work or receiving any payment for it (Wis. Admin. Code § ATCP 110.05(3)).

Signatures

By signing below, Owner consents in writing to the changes described in this Change Order, including any substitution of products or materials (Section 2) and any change in performance deadlines (Section 4), and each party acknowledges receiving a completed, signed copy.